कोसी प्रोजेक्ट केर असली नाम छल वैभेल प्रोजेक्ट लेकिन…… (एक शोधपूर्ण विचार अंग्रेजी मे)

Highest water flow was measured this year in the Saptakoshi River due to continuous rainfall, in Saptari, on Tuesday, September 13, 2016. Photo: THT

DR. L. N. SINHA INTERNATIONAL INSTITUTE OF ECONOMIC GROWTH, HUMAN RIGHTS, INFORMATION TECHNOLOGY & RESEARCH

REGISTERED UNDER SOCIETY ACT 21,1860 – REG. NO. 001218/608/2001-2 DT.20.10.2001.

File Photo: The Himalayan Times, Nepal

TENNESSE VALLEY AUTHORITY (U.S.A.) PATTERN WAVELL PROJECT OR KOSI PROJECT (1945)

Mrs. Dr. Jyoti Singh,

Chairman, Dr. L. N. Sinha international

Institute of Economic Growth, MIG-66,

1st Floor, Hanuman Nagar, Kankarbagh, Patna: 800020.

E-mail: [email protected] / rediff.com .

PH: 0612-397209.                       February 11, 1999.

 

Bihar gets a revenue loss of Rs. 264.5 crores per year due to  non-implementation   of TENNESSE VALLEY AUTHORITY (U.S.A.) PATTERN WAVELL PROJECT OR KOSI PROJECT (1945)  in Bihar. It is shame for politicians. Due to it, People are compelled to live in miserable conditions as they are born to die (in mysterious conditions i.e. due to flood and poverty etc). The Politicians are engaged in exploiting sentiments of people on caste and religion line for their own vested interests. Politicians are playing their game like Britishers i.e. divide and rule. Actually the present situation of people, is too much slave than that of the regime of Britishers. Unemployment rises up to more than 70% of the population and about 90% of the voters of the country.Now unemployed people have tortured and exploited a lot. So, there is necessity that the unemployed must be organized for their survival and justice. Now, The theory of exploitation of labour, is a part of theory of large exploitation of unemployed. So, the theory of straggle on communist theory basis as Lenin, Starlin and Mow had straggled, is finish/end now. Therefore, we are going to organize unemployed people for their survival and justice. JUSTICE will never be possible to find/get at politician level in India. A honest person will never get justice in India: Particularly in Bihar, not a single politician wants to do some thing for the benefit of people of whole Bihar. I reflect herewith one of the example. Which is as follows:

Jawaharlal Nehru and his colleagues told the people of Kosi that embankments were better than the dam ordered by Lord Wavell, Viceroy of India.Work on Kosi dam was in progress when Nehru stopped it and transferred the money to Bhakra  Nagal and  Damodar. Suffering Kosi people were given embankments which condemned  to even higher floods and a perpetual problem of evacuation and rehabilitation.The people of North Bihar were denied the agricultural and industrial prosperity which would have flowed from the TVA patterned Wavell project.

For fifty two years the managers of our affairs have been warned against construction of embankments which stop no floods . Only take them to another place. The misery  is not eliminated: it is only transferred.

Lord Wavell, the then Governor General of India, visited the Kosi area in 1945 and gave the Kosi project top priority among the several project in India. Kosi project has been directed by Mr. A.N. Khosla, chairman, Central water-power irrigation & navigation commission.We have opinion of the highest American as well as Indian experts that the Kosi project is technically feasible and financially sound.

It is urged that the total cost of the project in 1951 is Rs. 177 crores, is about half the annual budget of the Govt. of India and is, therefore, difficult to be managed in these days of financial strain. This argument is full of fallacies. First, for the construction of the dam and the barrage Rs. 60 crores only are needed, remaining Rs. 117 crores will be spent on producing power (1.9 million K.W.) and providing irrigation facilities (41 lakh acres) which will bring in a very large revenue to the state. Second, it compares the total cost of the project distributed over 15 years or so with the annual income of the Govt. of India and neglects the income that will accrue during the execution of the project, and will increase progressively. The Kosi project comprises of seven stages. In fact, if the first and second stages are started simultaneously, the total annual cost for the first two years will be 2.14 crores and 6.93 crores which will be contributed by the Govt. of India, Govt. of Bihar & Govt. ofNepal in 1951. Thus the annual cost of the project for the first two years is roughly equal to 0.52% and 1.75% of the total revenue of the three Govts. concerned. Revenue from the working of the project begins to appear in third year of work. Canal irrigation for three lakh acres of land can be had in the third year of the working of the second stage. Power for use will begin to be available on progressively larger scale every year, right from the third year of work. If we take into account the revenue from irrigation and power, the additional yield from irrigated land and additional gain from the use of power in forming, agricultural processing and industry,  the total money income in the fourth year of work will more than balance the total outlay for that year. Including the cost on account of the third stage of this project, which will be started in the fourth year of work, we have, in the fourth year, a surplus of about Rs.4.8 crores. As more and more land is brought under irrigation and more and more power is available for use, the surplus goes on mounting from year to year.

The financial aspect of the project which has been worked out in detail and an abstract of which has been given befow provides for the completion of the project in 15 years. Which is given below. The first four stages are completed in the sixth year. The total revenue from completed four stages in the 7th year of work will be about 5.69 crores. After deducting the amount spent on interest, depreciations, operations, maintenance, audit and account  etc., the surplus is more than 2 crores. If we add to this surplus the additional gain of  about Rs.63 crores from irrigation and power, the total comes to about Rs.65 crores.

The fifth stage may be taken up in the fifth year of the work and will then be completed in the fifteen year. The sixth stage may be taken up and completed in the eleventh year of the work. After the project is completed in the fifteenth year, there will be complete flood control, thus making about 3.5 lakh acres of land, perennially under water, cultivated and increasing the yield of about 9 lakh acres of flood effected land. Additional gain from flood control and fish culture in the embanked river channels and canals will come to  Rs. 25.6 crores. Additional yield from the irrigation of 41 lakh acres of flood free land will come to about 72 crores . Then there will be huge gain from 90,000 K.W.of power generated from the power plant of the first four stages. Total additional gain in the 16th year of the work will thus come to about 98.5crores. Again, net revenue alone from irrigation,power, navigation, recreation facilities at the dam and reservoir and fish culture in reservoir will come to about  Rs. 30.5 crore. Taking these two figures together, the total income in the 16th year comes to about  Rs. 129 crores.

The seventh stage that consists in installing power plant and developing electrical power of 1.8 million K.W. may be taken up in fourteenth year of the work. The total power capacity available in Indiais, at 1951, 2 million KW. The rapid development of 1.8 million KW. In the seventh stage will require efficient planning of industry, agriculture and transport not only of the kosi valley, but also of the whole country. In absence of the planned development of the Kosi valley from the beginning of the execution of the project, full fruits of the project can not be had. Assuming reasonable rapid development of the area on planned basis the available electrical energy can be developed in 10 years from the taking up of the seventh stage. Thus in the 24th year of the work, the revenue from power alone at the cheap rate of Rs: 0.02 (2 paisa) per unit will come to more than Rs. 21 crores. The total gross revenue in the 24th  year of the work will be about Rs. 57.5 crores and total net revenue 48.6 crore. The above calculation and statistic are based on data of year 1951.

On the basis of these estimates the net gain from the project upto the 16th year of its work comes to Rs. 1093 crore, that is , about 12% of the total national income of the country as a whole.

If we calculate present market cost ( 1.8 million K.W. Hydroelectric  X  @1.31/- per uint = Rs.234.8 crores and irrigation of  41 lakh acres land  X  @70/-  = Rs. 28.7 crores).The total revenue Rs. 264.5 crores is earned by the project directly besides fish culture etc. revenue.

Late Dr. Lakshmi Narayan Sinha, world reputed economist gave me all relevant information about the TVA Pattern Wavell project in detail. Dr. Sinha had been struggling for the revival of project right since 1951. Whose first book on economics “Capital & Employment”1964 was quoted by Nobel Laureate Gunnar Myrdal. Who he also gave the theories on welfare of economics before Amrtya Sen could. World market recession problem will solve only on the economic theories of Dr. Sinha. He had forecasted that all countries of the world should have to implement all his economic theories. It is the compulsion for the development of any country in the world. It seems true in the case of Bihar also. Because he wrote a book “WEALTH OF MITHILA” and he completed a thesis “LAND OF MITHILA”. Where he gave all relevant things about the development of North Bihar. At any cost, Bihar Govt. should have to implement all his advice for the development of Bihar either before the blood revolution or after the blood revolution. Because Bihar Govt. has no revenue to maintain there laws and orders situation in Bihar after the separation of Bihar.  I also got some relevant information about Kosi project from Prof. M. Mohiuddin, Ex. V. C., and Patna University.

Before the separation of Bihar, this project would must be revived. If it is not revived than politicians will have to face many difficulties in regards of earning revenue. Therefore, I request the politicians, world bank , multinationals and people work together for revival of the TVA  PATTERN WAVELL PROJECT as soon .

I have already brought to light it among the people of Bihar through my article- analysis of lord Wavell Kosi Project, Bihar v/s Dovell project, Maharastra -“Indian Economic Liberalization Policy” published dt.02.08.99 in “Aaj” Hindi Newspaper. “ARYAWART” – T.V.A. PATTERN WAVELL PROJECT, KOSHI RAJNITIGYO KE KUCHAKRA ME – DT.18.8.99, “AAJ”- BIHAR KA BATWARA AUR WAVELL PROJECT- DT.27.12.99, “TIMES OF INDIA”- WAVELL PROJECT REVIVAL COULD SOLVE FLOOD-RELATED PROBLEMS- DT.15.9.99. The paper cutting had brought to the knowledge of several politicians, CHIEF MINISTER, MINISTERS, EX-CHIEF MINISTER. But they did not do any thing  for the people and MLA does not raise the question in  Bidhan Shabha or Bidhan parishad. As if they have no any concern for the development of state, except their culture to exploit people. After the separation of “Jharkhand”. The time will come for the lesion for politicians and public servant of the state who they never think about the people of state. Where they are getting salary and misusing public money for their lug-jury. After the separation, the revenue of rest ofBihar is too much lower. It is not possible that the state govt. will pay the salary and pension from their collected revenue in the present situation. Therefore the whole administration will be collapsed. Only the politicians will be the targets of govt. employ as well as people. So, politicians will have to suffer much in near future. Again the slogan of revolution will rise from Bihar against political class people who is acting as Britishers. Mahatma Gandhi raised the slogan for independence from Bihar. I am forecasting these things on the basis of socio-economic system of Bihar as well as our country.. “ Ati Ka, Ant Hota hai” – it is the universal truth.

FINANCIAL ABSTRACT OF KOSI PROJECT AS ON 1951

( in crores of rupees)

Year    Sum        required           Revenue         Net requirement    Money value of Total income Capital        Other    benefits to the people from the project Outlay         expenses

1st                  2.1045     .0392                        0                         2.1437                      0                                       –   2.1437

2nd           6.37          .02035                     0                         6.9339                      0                                       –   6.9339

3rd           9.8184     .5546                    .2550                      10.1180                   5.25                                  –   4.868

4th           7.3470   1.0335                   1.202                      7.1784                   12.025                                     4.8465

5th             22.50        1.8672                   2.4580                21.9092                    34.15                                      12.2508

6th             15.50        2.3872                   4.2640                13.6152                    57.275                                   43.65

7th           5.00        3.0782                   5.6990                   2.3792                   63.15                                      60.7708

8th           5.00        3.2652                   5.6990                   2.5655                   63.15                                      60.58

9th           5.00        2.7577                   5.690                      2.6575                   63.15                                      60.4925

10th         5.00        3.6362                   5.690                      2.9365                   63.15                                      60.2135

11th          13.00        4.1712                   5.690                   11.4715                    63.15                                      51.6784

12th         5.00        4.3952                   6.1190                   3.2755                   72.95                                      69.6745

13th         5.00        4.5812                   6.1190                   3.4655                   72.95                                      69.4849

14th       11.00        4.8804                   6.1190                   9.7637                   72.95                                      69.4844

15th          11.00        5.2898                   6.1190                10.1741                    72.95                                      62.7759

16th         6.00        6.6257                43.419                 – 30.7240                    98.5128                             129.2368

17th         6.00        6.9161                41.41                    – 35.8932                    98.5128                             134.4060

18th         6.00        7.2065               49.169                  – 35.8932                    98.5128                             134.4060

YOURS TRULY

( Jyoti Singh), Economist.

Daughter in law’s   late Dr. L.N. Sinha, Eminent Economist of world.

MIG-66,Hanuman Nagar, Kankarbag, Patna – 800 020. Ph:367209.

Date:11.02.1999.

Email: [email protected]

[email protected]

[email protected]

साभारः https://mymotherlandbihar.wordpress.com/2011/08/07/wavell-project-or-kosi-project-1945/